Project Information

ADCOP will originate from Habshan in Abu Dhabi, which is presently the collection centre for the bulk of Abu Dhabi's onshore crude oil production. The pipeline will terminate at Fujairah. It has been designed for transporting 1.5 MMBPD of crude oil from ADCO facilities at Habshan over a distance of 370 km to an oil terminal in Fujairah for export through offshore loading facilities. The crude - Murban blend - will be carried through a single 48 inch diameter pipeline. The Project comprises the Pipeline, Pumping Station in Habshan and Suieihan main oil terminal at Fujairah, offshore loading facilities and other associated facilities.

 
 
 
 

Scope Of Project

Construction of
  1. A 400 km, 48 inch diameter pipeline including a 14 km submarine section, with a designed rated delivery capacity of 1.5 million bpd
  2. A connecting , initial,intermediate and terminal station
  3. 3 offshore single-point mooring devices
  4. Storage tanks.
 
 
 
 
 

Project Schedule

  1. Conceptual Design completed by Tebodin- 2006
  2. Award of Project Management Consultancy Contract to ILF CONSULTING ENGINEERS - April 2007
  3. Award Front End Engineering Design to Worley Parsons - September 2007
  4. Award of EIA Study to URS Cooperation - September 2007
  5. Award of Topographical Survey to MAPS GEOSYSTEMS- September 2007
  6. Award of Geotechnical Survey to FUGRO MIDDLE EAST/ARAB CENTRE FOR ENGINEERING STUDIES - September 2007
  7. Appointment of EPC Contractor CPECC and Start of Design and Construction activities - I./II. Quarter 2008
  8. Start commissioning: End 2010